Service roll out plan

Detailed roll out plan coming soon!

Here is our timeline for our service roll out

  • March 14th

    We have begun construction!

  • March 15th

    Pour concrete foundation for our new building.

  • March 17th

    Construction and erection of stud walls.

  • April 2nd

    Installation of trusses and roof decking.

  • April 4th

    Installation of shingles.

  • April 8th

    Wallace Tower to pour concrete footing for tower base.

  • April 15th

    Tower to be put into position.

  • April 21st

    Building construction complete.

  • April 24th

    Fiber installation.

  • May 17th

    Service roll out!